28/10/08
|
Installation of four monitoring wells on the
source property directly down-gradient of the spill area. |
Completed
(28/10/08) |
|
28/10/08
|
Frequency has changed from twice a week to once
a week. |
on-going |
|
30/10/08
|
Removal of product from the floor of the building
and on-site septic tank. |
Completed
(30/10/08) |
|
30/10/08
|
Recovery of product from the on-site potable
well. An on-site water treatment system is treating impacted
water to potable water standards. Treated water is being discharged
into a drainage ditch. |
on-going |
|
30/10/08
|
Test pitting program on source site (to south
of building). |
Completed
(30/10/08) |
|
04/11/08
|
Installation of on-site treatment system for
impacted groundwater recovered from the on-site potable well.
|
Completed (18/12/08) |
|
05/11/08
|
Installation of monitoring wells between the
spill area and the adjacent domestic wells located along Route
10. |
Completed
(05-06/11/08) |
|
06/11/08
|
Soil assessment in area of septic system. |
Completed
(08-09/11/08) |
|
06/11/08
|
Surveying to tie in the top of casing elevations
for private wells. |
Completed
(06/11/08) |
|
12/11/08
|
Sampling of soil from beneath the building's
floor slab. |
Completed
(12-13/11/08) |
|
25-11-08
|
Installation of deep monitoring wells. |
Completed
(11/12/08) |
|
16-01-09
|
Installation of dataloggers in the two deep
monitoring wells to allow for the collection of water level
data. |
Completed
(09/01/09) |
|
16-01-09
|
Collection of water level data from the two
deep monitoring wells. |
on-going |