| The Four Lane Trans-Canada Highway In New Brunswick |
||||||
|
|
||||||
|
Project: New four-lane highway Federal-Provincial Agreements: Canada Strategic Infrastructure Fund, Canada/New Brunswick Strategic Infrastructure Agreement, Border Infrastructure Fund Length: 12 km Number of Structures: 3 grade separations Number of Interchanges: 1 Status: Opened to traffic in 2007 Contractors: Clarence Daigle & Fils Ltée, Dexter Construction Ltd., Redem Construction Ltd., Matt Harris and Son Ltd., Maliseet Capital Construction/Tobique Economic Development Construction Facts:
Interesting Facts: 248,248 of truck-loads of material was hauled. If each load was represented by a dump truck and each truck was lined up bumper to bumper, the line would be 3,000 km long. | ||||||
|
The Four Lane Trans-Canada Highway in New Brunswick
|
||||||