Schedule - Completing the Trans-Canada Highway in New Brunswick Environmental determination expected for Pokiok to Longs Creek: November 2003 Clearing and Grading contracts called for Pokiok to Longs Creek from Allandale Rd. to Gibson Settlement Rd.: November 2003 Opening of 65 kilometres of Trans-Canada Highway: November 2003 Issue Request for Qualifications (RFQ): December 2003 Evaluate qualifications (responses to RFQ): January/February 2004 Select shortlist of three most qualified proponents: February/ March 2004 Issue Request for Proposals (RFP) to shortlisted proponents: March 2004 Land Assembly for Pokiok to Longs Creek expected to be complete: March 2004 Environmental determination expected for Grand Falls to Woodstock: March 2004 Evaluate proposals (responses to RFP) for Grand Falls to Woodstock: Summer 2004 Construction at Victoria St. interchange in Edmundston, Hodgdon Rd. and Lockhart Mill Rd. interchanges in Woodstock, East Fredericton High-Speed Connector, Pokiok to Longs Creek: Summer 2004 Land assembly complete for Grand Falls to Woodstock: August 2004 Select preferred proponent: October 2004 Opening of Victoria Street interchange in Edmundston, Hodgdon Rd. and Lockhart Mill Rd. interchanges in Woodstock, and East Fredericton High-Speed Connector: Fall 2004 Negotiation and sign agreement with preferred proponent for Grand Falls to Woodstock: Late Fall 2004 Clearing on Grand Falls to Woodstock: Winter 2004-05 Construction begins: Spring 2005 Open Pokiok to Longs Creek to safe traffic operations: Fall 2006 Open Grand Falls to Woodstock to safe traffic operations: Late Fall 2007 Completion of any other related project activities: Summer 2008 |