Lameque Shippagan Bridge concrete repairs

The current Lameque Shippagan Bridge is undergoing mechanical, electrical and steel repairs to the lift span as well as phased concrete repairs to maintain safe traffic flow while planning for a future replacement.

Overview

The Lameque Shippagan Bridge (L100) is the only land connection for Lamèque and Miscou Islands, serving a significant population and supporting critical services and the region’s fishing industry. Rehabilitation is ongoing. Design activities, including environmental approvals, property acquisition, and funding coordination, were started in spring/summer 2025. Engineering design will take at least 3 years to complete with construction expected to take 4–5 years.

Lameque Shippagan Bridge
Lameque Shippagan Bridge

Progress

Phase Status
1 - Phase one has been completed. Completed
2 - Replace mechanical, electrical and control systems. Install power back-up and complete the recently added phase 4 steel repairs as both phases are being completed by the Contractor. Installation to begin in September of 2025 after the seasonal lobster and crab fishing seasons end. Construction is anticipated to be completed by March 2026.
3 - Phase three has been completed. Completed
4 - Steel work included in Phase 2 Contract Ongoing
5 - Concrete Repair to maintain bridge safety and current weight capacity by completing repairs to abutments, piers and girders. Completed
Ongoing Concrete Repairs: Annual inspections will be conducted to assess significant concrete repair requirements, and a contract will be prepared to complete the necessary work during each construction season (2026-2030). Ongoing
New Bridge Design (2025 – Ongoing): Plan for long-term bridge replacement while maintaining current structure. The preliminary design phase is underway, including environmental and geotechnical field investigations, which will provide bases for an Environmental Impact Assessment (EIA).