Cost shared with the federal goverment.
Overview
Route 11 extends from Shediac to Campbellton. It handles up to 14,300 vehicles daily.
Progress
| South side of Shediac River to south side of Cocagne River twinning | Completed |
| North side of Cocagne River (Murray Brook) to south side of Little Bouctouche River (Ward Rd.) Twinning | Completed |
North of Bouctouche
Twenty-four culverts will be installed along the highway starting in 2022. An average of four to six culverts will be replaced per year. All replacements are expected to be complete in late fall 2027.
North of Cocagne
Thirteen passing lanes are planned to be added to the existing highway which started in 2023. An average of four to five passing lanes will be added per year. All additions are expected to be complete by the fall of 2026. This project is broken down into four phases, with the first two phases completed.
| Phase | Status |
|---|---|
| 1 - Work included the addition of four passing lanes with work beginning in September 2023 and concluding in December 2023. | Completed |
| 2 - Work included the addition of 4 passing lanes with work beginning in May 2024 and concluding in November 2024. | Completed |
| 3 - Work includes the addition of up to four passing lanes. | Four tenders have been advertised in 2025 with work concluding in the fall of 2025. |
| 4 - Work includes the remaining one passing lane. | Advertised in August 2025 and awarded in September 2025 with work concluding in the summer/fall of 2026. |