Overview
The Little Tracadie Bridge #1 (DTI Asset # L690), locally known as the Snowball Bridge, is a 155.54 m long, six-span rolled steel beam structure built in 1963, carrying Rue Principale Street over Rivière Du Petit-Tracadie River. The bridge connects downtown Tracadie to the north side of the municipality.
Due to severe deterioration, significant rehabilitation needs have been identified, particularly for the piers and the deck. The rehabilitation project aims to maintain a safe and reliable crossing of the Rivière Du Petit-Tracadie River.
Progress
Phase 1 – Bridge Deck Removal (November 2025 – April 2026) - Completed
Phase 2 – Substructure and Superstructure Rehabilitation (July 2026 – Fall 2027)
Closures
Full bridge closure is required during the rehabilitation works. Now that the first phase has been completed, the rehabilitation work will focus on rebuilding the deck to allow the bridge to open to traffic in late fall 2026.
The substructure rehabilitation will continue until fall 2027 with the bridge open to traffic. Temporary lane closures and short duration full bridge closures may be required during the second phase substructure works. Those temporary lane closures will be restricted to non-peak hours and weekends/holidays. Planned closures will be communicated to the public and industry through various channels, including radio, social media, and the NBDTI projects webpage. Emergency services will be notified in advance of any closures.