Registration documents are prepared by proponents and made available in the language in which they were received by the Department of Environment and Local Government.
Project number: 1489
Date registered: 2018/01/12
Proponent: New Brunswick Power Corporation (NB Power)
Appendices:
- Appendix A - Additional Information (Requirements Of New Brunswick Eia Guide) (PDF 148 KB)
- Appendix B - Environmental Attributes Of The Row For The Modernization Of Electrical Infrastructure Near Neguac, New Brunswick (PDF 307 KB)
- Appendix C - Freshwater Fish And Fish Habitat, Vegetation And Wetlands, And Wildlife And Wildlife Habitat Features Observed In The Local Assessment Area (PDF 8.7 MB)
- Appendix D - Vegetation And Wetlands, And Wildlife And Wildlife Habitat Environment Survey Data (PDF 2.5 MB)
- Appendix E - Additonal Information On Public Involvement (PDF 7.4 MB)
Description: The proposed project consists of the construction and operation of a new substation and new transmission line (Phase 1), and the decommissioning of an existing substation and two existing transmission lines (Phase 2) near Neguac, NB.
Location: Northumberland & Gloucester
EIA specialist: Justin Chase
Status: Certificate of Determination issued (PDF 165 KB)
Date of decision: 2018/07/23
Project number: 1490
Date registered: 2018/01/22
Proponent: NB Power Corporation
- Environmental Impact Assessment (EIA) Report: Fundy Isles Submarine Cables Replacement Project, New Brunswick (PDF 315 KB)
- Section 1.0 - Introduction (PDF 791 KB)
- Section 2.0 - Project Description (PDF 2.6 MB)
- Section 3.0 - Environmental Setting (PDF 3.2 MB)
- Section 4.0 - Environmental Assessment Methods and Scope (PDF 1.5 MB)
- Section 5.0 - Assessment of Environmental Effects on the Atmospheric Environment (PDF 883 KB)
- Section 6.0 - Assessment of Environmental Effects on the Terrestrial Environment (PDF 1.4 MB)
- Section 7.0 - Assessment of Environmental Effects on the Marine Environment (PDF 8.4 MB)
- Section 8.0 - Assessment of Environmental Effects on Water Resources (PDF 638 KB)
- Section 9.0 - Assessment of Environmental Effects on the Socioeconomic Environment (PDF 1.1 MB)
- Section 10.0 - Assessment of Environmental Effects on Heritage Resources (PDF 1.2 MB)
- Section 11.0 - Assessment of Environmental Effects on Commercial, Recreational and Aboriginal Fisheries (PDF 3 MB)
- Section 12.0 - Assessment of Environmental Effects on Current Use of Land and REsources for Traditional Purposes by Aboriginal Persons (PDF 1.4 MB)
- Section 13.0 - Assessment of Effects of the Environment on the Project (PDF 3.6 MB)
- Section 14.0 - Assessment of Accidents, Malfunctions, and Unplanned Events (PDF 202 KB)
- Section 15.0 - Assessment of Cumulative Environmental Effects (PDF 1.2 MB)
- Section 16.0 - Summary of Mitigation (PDF 204 KB)
- Section 17.0 - Summary and Conclusions (PDF 143 KB)
- Section 18.0 - References (PDF 274 KB)
- List of Appendices (PDF 5.5 MB)
Description: The proponent proposes to install and operate two new submarine electrical transmission cables to Fundy Isles (Deer Island, Campobello Island and Grand Manan) from mainland New Brunswick.
Location: Charlotte
EIA specialist: Sheila Goucher
Status: Certificate of Determination issued (PDF 175 KB)
Date of decision: 2018/09/20
Project number: 1491
Date registered: 2018/02/23
Proponent: Village de Le Goulet (PDF 4.3 MB)
Description: The project consists of the restoration of sand on the Village of Le Goulet’s dune system as a climate change adaptation measure.
Location: Gloucester
EIA specialist: Pierre Doucet
Status: Certificate of Determination issued (PDF 165 KB)
Date of decision: 2018/03/16
Project number: 1492
Date registered: 2018/02/28
Proponent: Pecheries Ste-Cecile Inc. (PDF 11.5 MB)
Description: The proponent is proposing to expand the existing M&N Seafood Plant in Sainte-Cécile (which will continue to process herring roe) with the addition of a separate building that will house a lobster and crab processing line.
Location: Gloucester
EIA specialist: Pierre Doucet
Status: Certificate of Determination issued (PDF 169 KB)
Date of decision: 2018/10/09
Project number: 1493
Date registered: 2018/04/16
Proponent: DFO-SCH (PDF 7.2 MB)
Description: The project consists of the dredging of Shippagan Gully and the construction of a 200 meter long breakwater.
Location: Gloucester
EIA specialist: Duane Mercer
Status: Certificate of Determination issued (PDF 160 KB)
Date of decision: 2019/09/06
Project number: 1494
Date registered: 2018/04/16
Proponent: Wisokolamson Energy LP
- Executive Summary (PDF 1 MB)
- Table of Contents (PDF 202 KB)
- Section 1 - Introduction (PDF 227 KB)
- Section 2 - First Nations and Public Involvement (PDF 149 KB)
- Section 3 - Project Description (PDF 1.6 MB)
- Section 4 - Description of the Existing Environment (PDF 5.7 MB)
- Section 5 - Identification of Environmental Effects and Mitigation (PDF 282 KB)
- Section 6 - Residual Environmental Effects and Determination of Significance (PDF 230 KB)
- Section 7 - Summary of Proposed Mitigation (PDF 176 KB)
- Section 8 - Follow-up Monitoring (PDF 98 KB)
- Section 9 - References (PDF 165 KB)
Appendices:
- Appendix A - Clearances and Approvals (PDF 8.8 MB)
- Appendix B - Preliminary Indigenous Knowledge Study (PDF 275 KB)
- Appendix C - Letter of Support (PDF 116 KB)
- Appendix D - Noise Impact Assessment (PDF 13.2 MB)
- Appendix E - Bird Inventory Report (PDF 3.9 MB)
- Appendix F - Bat Inventory Report (PDF 25.6 MB)
- Appendix G - Archaeology Report (PDF 72 KB)
- Appendix H - Visual Impact Assessment (PDF 22.8 MB)
- Appendix I - Shadow Flicker Assessment (PDF 8.2 Mo)
- Appendix J - Eletromagnetic Interference Study (PDF 48.9 MB)
Description: The proposed project involves the construction of five wind turbine generators with a capacity of 18 Mega Watts and a new substation. The proposed project is located on crown land and private lands south of New Ireland Road.
Location: Albert
EIA specialist: Pierre Doucet
Status: Certificate of Determination issued (PDF 176 KB)
Date of decision: 2018/09/21
Project number: 1495
Date registered: 2018/06/25
Proponent: Sagewill Enterprises Ltd.
- Sagewill Limestone Quarry EIA Registration (PDF 264 KB)
- Environmental Management Plan (PDF 4.6 MB)
- Mining Plan (PDF 8.9 MB)
- Appendices (PDF 8.3 MB)
- Addendum Report (PDF 7.2 MB)
Description: The proposed project involves the development of a limestone quarry north of Hammond River near the community of French Village.
Location: Kings
EIA specialist: Pierre Doucet
Status: Awaiting additional information
Project number: 1496
Date registered: 2018/06/27
Proponent: The Village of Fredericton Junction (PDF 4.4 MB)
Description: The Village is proposing to undertake a ground water exploration program to find an alternate source of drinking water.
Location: Sunbury
EIA specialist: Sheila Goucher
Status: Certificate of Determination issued (PDF 138 KB)
Date of decision: 2020/09/30
Project number: 1497
Date registered: 2018/07/10
Proponent: The Department of Transportation and Infrastructure
- Regulator DRAFT REPORT Environmental Impact Assessment Registration Document (PDF 3.3 MB)
Northwest Miramichi River No. 1 (Anderson) Bridge Replacement Miramichi, New Brunswick - Appendix A (PDF 1.2 MB)
- Appendix B (PDF 2.9 MB)
- Appendix C (PDF 1.9 MB)
- Appendix D (PDF 2.5 MB)
- Appendix E (PDF 4.3 MB)
- Appendix F (PDF 2.2 MB)
- Appendix G (PDF 3.4 MB)
- Appendix H (PDF 4.5 MB)
- Appendix I (PDF 2.2 MB)
- Appendix J (PDF 3.1 MB)
Description: The proponent proposes to remove the Northwest Miramichi River No. 1 (Anderson) Bridge along Route 8 and fully replace it with a new bridge slightly upstream.
Location: Northumberland
EIA specialist: Pierre Doucet
Status: Certificate of Determination issued (PDF 134 KB)
Date of decision: 2020/05/06
Project number: 1498
Date registered: 2018/09/18
Proponent: Trevali Mining (New Brunswick) Ltd. (PDF 4.1 MB)
Description: Trevali is proposing to construct a new tailings management facility (TMF) at the Caribou mine in 2 stages.
- Stage 1: Would provide additional tailings storage capacity for the current life of mine. This includes a new tailings dam, emergency spillway, TMF basin, polishing pond and dam, and a water treatment facility.
- Stage 2: Would consist of raising the Stage 1 dam which would inundate portions of the mine in support of mine closure and potentially provide additional storage capacity. This stage would involve a dam raise, expanded emergency spillway and tailings basin, and construction of an alternative access road.
Location: Restigouche
EIA specialist: Sheila Goucher
Status: Inactive
Project number: 1499
Date registered: 2018/08/10
Proponent: The Department of Fisheries and Oceans – Small Craft Harbours (DFO-SCH) (PDF 4.1 MB)
Description: The proposed project consists of the construction of a new containment cell for the New Mills Harbour.
Location: Restigouche
EIA specialist: Cassandra Colwell
Status: Certificate of Determination issued (PDF 166 KB)
Date of decision: 2018/12/21
Project number: 1500
Date registered: 2018/08/17
Proponent: Tourbières L.M. Ltée
- Étude d'impact environnemental - Tourbière #564 Région de St-Léolin, Nouveau-Brunswick (PDF 8.5 MB)
- Annexe A (PDF 320 KB)
- Annexe B (PDF 2 MB)
- Annexe C (PDF 958 Ko)
- Annexe D (PDF 1.5 MB)
- Annexe E (PDF 453 KB)
- Annexe F (PDF 1.2 MB)
- Annexe G (PDF 2.2 MB)
- Annexe H (PDF 655 KB)
Description: The proponent is proposing to harvest peat by developing Bog #564, near Saint-Léolin, which will include the construction of an access road, sedimentation ponds, and drainage channels.
Location: Gloucester
EIA specialist: Pierre Doucet
Status: Certificate of Determination issued (PDF 131 KB)
Date of decision: 2019/12/02
Project number: 1501
Date registered: 2018/09/13
Proponent: The Village of Grand Manan
- Village of Grand Manan - Aquatic Centre and Wellness Facility (PDF 1.7 MB)
- Appendix A (PDF 217 KB)
- Appendix B (PDF 1.7 MB)
- Appendix C (PDF 1.4 MB)
- Appendix D (PDF 279 KB)
- Appendix E (PDF 998 KB)
- Appendix F (PDF 1.2 MB)
- Appendix G (PDF 265 KB)
- Appendix H (PDF 166 KB)
- Appendix I (PDF 2.2 MB)
- Appendix J (PDF 1.3 MB)
- Appendix K (PDF 1.6 MB)
- Appendix L (PDF 3.5 MB)
Description: The Village is proposing to construct and operate an Aquatic Centre and Wellness Facility consisting of a 5-lane lap pool, a children’s pool with a slide, a spectator area, walking track, ancillary support area, and revenue spaces.
Location: Charlotte
EIA specialist: Sheila Goucher
Status: Determination review in progress
Project number: 1502
Date registered: 2018/09/10
Proponent: Fisheries and Oceans Canada – Small Craft Harbours (PDF 1.6 MB)
Description: The proponent is proposing to decommission three wharfs on Campobello Island and Deer Island in the locations of Curry Cove, Chocolate Cove, and Richardson Wharf.
Location: Charlotte
EIA specialist: Cassandra Colwell
Status: Certificate of Determination issued (PDF 160 KB)
Date of decision: 2019/02/14
Project number: 1503
Date registered: 2018/09/12
Proponent: Fisheries and Oceans – Small Craft Harbours (DFO-SCH) (PDF 977 KB)
Description: The proposed project consists of expanding the existing containment cell at the Pointe-Sapin Harbour and dredging the harbour basin.
Location: Kent
EIA specialist: Rachelle Voisine
Status: Certificate of Determination issued (PDF 167 KB)
Date of decision: 2018/02/02
Project number: 1504
Date registered: 2018/09/17
Proponent: The Department of Transportation and Infrastructure (PDF 5.8 MB)
Description: The proponent proposes to decommission the existing sewage treatment lagoon at Harvey High School.
Location: York
EIA specialist: Rachelle Voisine
Status: Certificate of Determination issued (PDF 167 KB)
Date of decision: 2019/01/31
Project number: 1505
Date registered: 2018/09/13
Proponent: Fisheries and Oceans Canada – Small Craft Harbours (DFO-SCH)
- Underwater Benthic Habitat Survey (Final), Maces Bay Department of Fisheries and Oceans Canada Small Craft Harbour (DFO-SCH), Maces Bay, Charlotte County, New Brunswick, SCH No. 2588, DFRP No. 04031, RPIS No. MS 02588 (PDF 1.6 MB)
- Project Effects Determination Report (PDF 4.9 MB)
Description: The project consists of decommissioning a derelict small craft harbour facility. The work will involve removal of the end of an existing wharf and covering the remainder with rock to stabilize it and create a breakwater.
Location: Charlotte
EIA specialist: Sheila Goucher
Status: Certificate of Determination issued (PDF 167 KB)
Date of decision: 2018/12/07
Project number: 1506
Date registered: 2018/09/20
Proponent: Wocawson Energy Project
- Environmental Impact Assessment Registration (PDF 12.3 MB)
- Appendix A (PDF 1 MB)
- Appendix B (PDF 888 KB)
- Appendix C (PDF 879 KB)
- Appendix D (PDF 6.7 MB)
- Appendix E (PDF 4.9 MB)
- Appendix F (PDF 5.5 MB)
- Appendix G (PDF 5.2 MB)
- Appendix H (PDF 4.4 MB)
- Appendix I (PDF 3.7 MB)
- Appendix J (PDF 1.1 MB)
- Appendix K (PDF 288 KB)
- Appendix L (PDF 224 KB)
- Appendix M (PDF 348 KB)
- Wocawson Energy Project Addendum - Transmission Line Access Route Monitoring (PDF 6.7 MB)
- Wocawson Energy Project Addendum - New Proposed Layout (PDF 2.6 MB)
- Environmental Management & Protection Plan (PDF 1.1 MB)
- Acoustic Bat Survey Report (PDF 3.5 MB)
- Addendum to Bird and Bird Habitat Report (PDF 2.5 MB)
- Archaeological Testing At A Proposed Wind Farm Transmission Line near Sussex, NB (PDF 8 MB)
Description: The proposed project involves the construction of 6 to 12 wind turbine generators with a capacity of 20 to 40 Mega Watts, a new substation and a new transmission line. The proposed project is located on crown land 20 km northeast of Sussex, New Brunswick.
Location: Kings
EIA specialist: Pierre Doucet
Status: Certificate of Determination issued (PDF 182 KB)
Date of decision: 2019/03/12
Project number: 1507
Date registered: 2018/10/29
Proponent: Repairs to Retaining Wall at 11 Southers Road (Bayswater) Adjacent to Wetland
- Environmental Impact Assessment Registration (PDF 21.9 MB)
- Wetland Functional Assessment Report (PDF 6.9 MB)
Description: The proposed project involves the construction of a new retaining wall within a regulated wetland to support an existing retaining wall which has become eroded.
Location: Kings
EIA specialist: Cassandra Colwell
Status: Certificate of Determination issued (PDF 167 KB)
Date of decision: 2018/12/06
Project number: 1508
Date registered: 2018/11/02
Proponent: Hammond River Holdings Limited
- Environmental Impact Assessment Registration - Part 1 (PDF 10.1 MB)
- Environmental Impact Assessment Registration - Part 2 (PDF 8.6 MB)
- Environmental Impact Assessment Registration - Part 3 (PDF 10.2 MB)
- Environmental Impact Assessment Registration - Part 4 (PDF 4.7 MB)
- Environmental Impact Assessment Registration - Appendices (PDF 5 MB)
- Environmental Impact Assessment Registration - Erratum #1 (PDF 7.2 MB)
Description: The proposed project involves the development of an open pit quarry for the extraction of gypsum.
Location: Kings
EIA specialist: Patricia Holland
Status: Certificate of Determination issued (PDF 148 KB)
Date of decision: 2019/10/15
Project number: 1509
Date registered: 2018/11/20
Proponent: Fisheries and Oceans Canada – Small Craft Harbours (DFO-SCH)
- Environmental Impact Assessment Registration (PDF 5 MB)
- Environmental Impact Assessment Registration - Appendices (PDF 3 MB)
Description: The proponent proposes to construct a new containment cell, conduct other associated alterations, install a new floating wharf and dredge the harbour basin at the Anse-Bleue Harbour.
Location: Gloucester
EIA specialist: Rachelle Voisine
Status: Certificate of Determination issued (PDF 166 KB)
Date of decision: 2019/06/12
Project number: 1510
Date registered: 2018/11/23
Proponent: Berthe Comeau (PDF 4 MB)
Description: The proponent is proposing to expand their existing campground “Chalet & Camping de la Pointe” of 178 sites by adding eleven new sites with services, using an existing well and installing a sewage system.
Location: Gloucester
EIA specialist: Cassandra Colwell
Status: Certificate of Determination issued (PDF 220 KB)
Date of decision: 2019/08/28
Project number: 1511
Date registered: 2018/12/03
Proponent: Villa Sormany (PDF 11.9 MB)
Description: The proponent is proposing to develop a new potable water well for the Villa Sormany nursing home in Robertville.
Location: Gloucester
EIA specialist: Pierre Doucet
Status: Certificate of Determination issued (PDF 167 KB)
Date of decision: 2019/05/30
Project number: 1512
Date registered: 2018/12/18
Proponent: Domaine Nature Estates Subdivision (PDF 11.8 MB)
Description: The proponent is proposing to continue development of the existing subdivision, consisting of 88 lots. The proposed expansion will add an additional 80 lots and associated infrastructure.
Location: Westmorland
EIA specialist: Duane Mercer
Status: Certificate of Determination issued (PDF 193 KB)
Date of decision: 2020/02/07
Project number: 1513
Date registered: 2018/12/19
Proponent: At Landing (PDF 5.3 MB)
Description: The proponent proposes to expand their existing facility in Blacks Harbour by adding a sea cucumber cutting and blanching process.
Location: Charlotte
EIA specialist: Jillian Craig
Status: Certificate of Determination issued (PDF 129 KB)
Date of decision: 2021/06/07
Project number: 1514
Date registered: 2018/12/21
Proponent: Kelly Cove Salmon Ltd. (PDF 26.8 MB)
Description: The proponent proposes to expand the Johnson Lake Hatchery and upgrade the waste treatment system.
Location: Charlotte
EIA specialist: Rachelle Voisine
Status: Certificate of Determination issued (PDF 143 KB)
Date of decision: 2019/07/05